Wesley New Town Development

DSC_0218.JPG

Client
Heb Construction

Sector
Water and Rising Main

Construction of 7.2km of 280mm OD PE Rising Main including 13 air valves, 13 odour filters and 13 scour valves.  The construction was a combination of Horizontal Directional Drilling and open trenching with depths of 2m - 4.5m.

Construction of 3.2km of 250mm OD PE Water Main including 8 air valves, 6 fire hydrants and 15 sluice valves.  The Construction was a combination of Horizontial Directional Drilling and open trenching with depths of 2m - 3.5m.

We carried out all construction including pressure testing and disinfection as per Watercare Standards.

The project value was $4.2 million and was constructed over a 12 month period.